● On Track · Handover 2028 Verified 23 July 2026 · RERA

Athlon by Aldar Construction Update, September 2026

We track Athlon's build every month using the developer's footage and the Government of Dubai's independent RERA progress reports, so owners and buyers get the honest picture, not marketing.

Is Athlon on time? Yes. As of the latest independent Government of Dubai / RERA inspection (23 July 2026), both Athlon phases (projects 3143 and 3145) are audited as "Main Contract, Progressing": enabling and foundation works complete, structures rising, with envelope, MEP, finishes and infrastructure all underway on site. Handover is estimated for 2028.

Athlon by Aldar 1 · Project 3143

Wadi Al Safa 5 · Plot 10205 · 76 Horizon signature villas + 206 standard villas + 611 townhouses · RERA inspected 23 Jul 2026
Enabling
Foundation
Structure
Envelope / MEP
Finishes

RERA notes: enabling, foundation, structure, internal works, external envelope, MEP, internal finishes and infrastructure all progressing on site. Status audited as "Main Contract, Progressing."

Athlon by Aldar 2 · Project 3145

Wadi Al Safa 5 · Plot 10203 · 75 Pillars signature villas + 185 standard villas + 339 townhouses · RERA inspected 23 Jul 2026
Enabling
Foundation
Structure
Envelope / MEP
Finishes

RERA notes: enabling, foundation, structure, internal works, MEP and infrastructure all progressing on site; concrete structure and block with internal and external finishes. Status audited as "Main Contract, Progressing."

Source: Government of Dubai / RERA Independent Progress Monitoring Reports (projects 3143 and 3145, developer Aurora SPV 3 L.L.C.), inspected 23 July 2026. Construction imagery is RERA progress documentation, not a marketing render. Handover date is an estimate and subject to developer confirmation.